Yes. For Initial Surveys scheduled on or between July 1, 2024, and June 30, 2026, the organization may submit a detailed implementation plan that includes a timeline as evidence for applicable factors.
Implementation plans may be submitted for Initial Surveys for the following requirements until June 30, 2026:
-
HE 2, Element A.
-
HE 2, Element D.
-
HE 2, Element E.
-
HE 2, Element G.
-
HE Plus 3, Element C.
-
HE Plus 5, Element B.
-
HE Plus 5, Element E.